On duty 9-22 Okt 2025

9 otw ke attaka via santan, 
10 replace FE1105 CP by 3051SMV sekalian verify dgn PT dias. 
11 bravo inspek gas lift meter bareng pt dias
12 gsm, screening MO, sufri ke delta inspek gl meter with pt dias
13 function test di alpha with yasser, yudith ke J dan C inspek gl meter with pt dias, sufri ke M PM. 
14 function tes production, yudith ke F FS
15 standown meeting kebakaran di Dumai, meeting dgn wifgas, resetting satuan totalizer meter FE1105 jd MMSCFD. STA shutdown by GD HH. Banyak kebocoran di well area. 
16 acting 
17 training one sika
18 training onesika
19 GSM, SPRS, meeting gas lift meter, repair actuator GL Fox to B
20 yudith ke K pm n beberapa WO, wahyu ke J pm
21 yudith wahyu ke J function tes dan ganti PS IAC C1A, aku jumriadi parallel transmitter GL B4 dan update parameter 3095FC dan 3051SMV
22 wahyu, jumri inpect pipe at production. Aku yudith update parameter FE1105, prepare connect to PLC. 
Sore ke santan karena cak tria cs udah pindah ke rabu. Malem ke rumah jumriadi di bunga putih bareng ganz, reno, mifta, sufri. Lanjut malam ini ke balikpapan. 
23 off naik lion jam 6 transit sby. Jam 10 udah landing di bali. 

#Update gas CP
#Bikin report meter
#Pelajari PLC CP P
#Bikin draft handover
#Submit timesheet
#Deluge KRDP
#Ambil gas lift sampling
#Configure meter B
#Scafolding utk STA FD
#Email kamar santan
#Submit cuti
#Pm cek.list prod
#Actuator dr lawe
#Juliet LSLL Test
#Siapin material utk paralel B4
#Baikin actuator utk foxtrot, minta scafold
#Forward email sultan ke mudi
#PM cek list Cp delta
#Meter 303AB lapor zainal
#PSSR PLC Bravo
#WO deluge alpha? Msh open?
#Simpan compressor air dryer
#Liat tipe AI di PLC laptop
#Kirim lomba artikel