Friday, October 06, 2023

CUTI, SAT PLC BRAVO, PREPARE AUDIT SMK3

On duty 13-20 Sept 2023

13 otw ke attaka via propane
14 siapin TKI dan MKJSA untuk audit SMK3
15 lanjut siapin TKI n MKJSA
16 terminasi FD bravo, prepare migrasi, function test tipis2
17 Today plc bravo: 17 sep 2023
- termination cable Fire Detectors (14x3 ea) (contd)
- install new ESD station at shipping pump and boat landing and connect cable
- install tubing for solenoid ESD Loop
- install tubing for solenoid 3Way Wing Valve
- install tubing for Horn
- troubleshoot LT 105 indication
- edit HMI for V105 display pressure and level
- install new cable for LSH/LSHH sump caisson (continued)
18 Today 18 Sept 2023
- cont termination FD completed
- test connection FD01
- install Jbox solenoid Deluge Valve at well area
- install new cable for LSH/LSHH sump caisson
- connect cable horn FDHH
- conect cable solenoid for ESD loop, 3way wing valve, deluge valve separator area
19 Sept 2023
SAP dan Function test PT, LT, ESD Station, GD, FD, ESD Station, Solenoide valve. 

Finding and next planning: 
- replace relay shipping pump karna short
- install kabel WCP, slop pump, DFWP
- replace level switch LSHH dan LSLL slop tank karena rusak micro switchnya

Next prioritas 2:
- kabel start stop sump pump
- replace/conect cable pressure switch WCP

List Migrasi:
- 3 way wing valve
- deluge valve DV1 dan DV2
- SDV Gross dan Test
- ESD Station di shiping pump area dan landing boat sdh dipasang baru, nanti tinggal pindah support aja

20 di LQ aja bikin laporan dan handover
21 off duty maju 6 hari ambil cuti




No comments: